Removing solar panels for roof replacement, in short
Removing solar panels for roof replacement is a cost most owners never planned for. When a roof wears out under an array, the panels have to come off before the roof can be replaced and go back on afterwards. That work belongs to the solar company, and it adds cost and time to a job that would otherwise be simpler.
The way to avoid it is sequence. If the roof is near the end of its life, replacing it before the panels go on means the work happens once, with nothing in the way. If panels are already up, the replacement needs to be planned with the solar company so the two trades work in the right order.
This article explains how to judge whether a roof should be replaced before solar, what happens when an existing array has to come off, and how to coordinate the two companies involved. We handle the roof side. We do not remove, store or refit panels.
Sequence matters more than product
A solar array is installed to stay on a roof for many years. The roof beneath it has its own clock, set by its age, its materials and the climate. If the roof’s clock runs out first, the array has to be taken off, the roof replaced, and the array put back.
That is a two-trade job with real costs: the solar company’s work to remove and refit the panels, the roofing work itself, and the time the system is not producing power. None of it improves the array. It only exists because the roof and the panels were not matched.
When panels go on a roof with plenty of life left, or on a new roof, that sequence is avoided. The roof and array age side by side, and by the time the roof needs replacing, the array may be due for review too.
So the most valuable number in the whole decision is the roof’s remaining life.
Roof age for solar panels
The guiding principle is simple: the roof under an array should have at least as much remaining life as the array is expected to stay in place. Matching the two means the array never outlives the roof it sits on.
Judging remaining life is the hard part, because a roof can look sound from the street while the layer beneath its covering is near the end. On a tile roof especially, the tiles often outlast the underlayment beneath them, and that layer is what decides when the roof needs work.
The City of Scottsdale homeowner guide lists flashing and felt underlayment among the inspections for a re-roof, reflecting how central that layer is. On shingle roofs, granule loss, curling and cracking show age more visibly.
An assessment before solar should therefore report on the waterproofing beneath the covering, not just on the covering itself.
Many local roofs are at the age where this matters
A City of Scottsdale homeowner guide records that clay and concrete tile became the roofing material of choice in the 1990s. Census American Community Survey 2023 five-year estimates put about 74 percent of Scottsdale’s housing units as built before 2000, with the 1990s the largest single decade.
That combination describes a large number of tile roofs that have now been in place for several decades (US Census Bureau). Those survey estimates carry margins of error, but the pattern is clear: many houses considering solar today have roofs from that era.
The climate adds to it. At the Scottsdale Municipal Airport weather station, NOAA’s 1991 to 2020 normals average about 93 days a year at or above 100 degrees Fahrenheit (NOAA NCEI), and the layer beneath a roof covering has spent every one of those days in the heat.
For many owners, the honest answer to roof first or panels first is roof first.
Cases where the roof should come first
Replace the roof before solar goes on when the assessment shows the waterproofing beneath the covering is near the end of its life, when the covering itself is worn, cracked or failing, or when the roof has a history of leaks. In each case, the roof will need work during the array’s life.
The roof should also come first if its structure needs attention. An array adds weight and wind load, and any structural work is far simpler before panels are mounted than after.
Doing the roof first also allows the array’s mount positions to be planned into the new roof, with flashings installed as part of the roofing work rather than added afterwards. That generally produces better-sealed penetrations.
The tile-specific questions are covered in solar panels on a tile roof.
Cases where panels can go on first
Panels can reasonably go on first when the roof is relatively new, when its waterproofing has been assessed and has plenty of remaining life, and when the structure can carry the array. In that case there is no reason to replace a sound roof just because solar is coming.
Even then, the roof side of the installation deserves attention. Mount flashing, tile handling and the condition of the roof around the array all affect how well the roof performs for the life of the system.
It is worth recording the roof’s condition before installation, with photographs, so that any later problem can be traced to its cause. That record also helps if the question of who is responsible for damage ever arises.
Where panels and roofs interact, and where damage really comes from, is covered in do solar panels damage your roof.
Panels already up and a roof that needs replacing
If an array is already on a roof that now needs replacing, the replacement has to be planned with the solar company. They remove the panels and racking, and store or protect them while the roof is replaced. Once the new roof is on, they refit the array.
The roofing work in between is the same as any replacement, with one addition: the mount positions need to be planned and flashed into the new roof so the array can go back on properly.
The order matters. The solar company must finish removal before roofing starts, and the roof must be finished, with mount flashings in place, before the solar company returns. Gaps between the two leave the house exposed or the array idle longer than necessary.
That coordination is where most problems arise, and where a clear plan saves time and cost.
Coordinating the two trades
The owner usually ends up as the link between two companies who each handle half of the job. Setting out the sequence in writing, with dates and responsibilities, prevents the most common problems: the roofer arriving before the panels are off, or the solar company returning before the mount flashings are ready.
Agree who is responsible for what. The solar company handles the array, its wiring and any monitoring. The roofer handles the roof and the flashings at each mount. Each should know what the other needs from them.
Our solar-ready roofing in Scottsdale page covers the roof side and how we coordinate with the solar company on a replacement. We do not remove, store or refit panels; that remains the solar company’s work.
Before work starts, ask both companies how their warranties are affected, and keep their answers in writing. Photographs of the array and the roof before removal, and of the new roof before the panels go back, give both companies and the owner a shared record of what was handed over at each stage.
Monsoon timing and planning ahead
The National Weather Service office in Phoenix defines the monsoon season as June 15 through September 30, naming damaging winds and torrential rainfall among its hazards (NWS Phoenix). A roof that is open, or an array that is off, is most exposed in that season.
That makes the cooler, drier months the better time for a coordinated replacement. Planning ahead also gives both companies time to schedule, which reduces the chance of gaps between the two stages.
If an ageing roof under an array is already leaking, waiting is not always an option, but even then a short delay to agree a clear sequence with both companies usually saves more than it costs. A temporary measure to stop water entering, arranged with a professional, can buy that time.
Lead times matter too. Solar companies schedule removals and refits around their own installation work, and roofers schedule replacements around the weather. Asking both for their availability before committing to dates avoids a roof sitting half-finished while one trade waits for the other.
Community rules and the sequence
Owners in planned communities sometimes worry about whether an array that comes off can go back on. Under Arizona Revised Statutes 33-1816, an association may not prohibit solar energy devices, and may adopt placement rules only where they do not prevent installation, impair functioning or adversely affect cost or efficiency.
A prevailing homeowner may recover reasonable attorney fees and costs under the same section (Arizona Revised Statutes 33-1816). Associations may still have rules on roofing materials and colours, which apply to the new roof whether or not panels go back on.
It is worth checking those roofing rules before choosing materials for the replacement.
Where to start
If solar is planned, start with a roof-side assessment that looks beneath the covering. If the roof has less life left than the array will need, replace it first and plan the mounts into the new roof. The wider context is in our guide to solar-ready roofing.
If panels are already up and the roof is failing, contact the solar company and a roofer together, and agree the sequence in writing before anything starts.
One safety point. Roofs with arrays are awkward and dangerous to move around on, and the City of Scottsdale’s homeowner guide says roof work can be dangerous and lethal for the inexperienced. If you would rather have someone look at the roof, Residential Roofing Scottsdale works across Scottsdale and the surrounding Valley. Call (480) 919-1173.
Frequently asked questions
These are the questions homeowners in this area ask most often when solar and an ageing roof meet, either before an installation or when a roof under an existing array starts to fail. Each answer is kept deliberately short and covers the roof side and the sequence, not the panels themselves.
Should I replace my roof before installing solar panels?
If the roof has less remaining life than the array is expected to stay in place, usually yes. Replacing it first means the work happens once, and mount flashings can be planned into the new roof.
How old is too old a roof for solar panels?
Age alone does not decide it. What matters is the remaining life of the waterproofing beneath the covering compared with how long the array will stay. A roof-side assessment should report on that layer, not just the surface.
What happens to solar panels during a roof replacement?
The solar company removes the panels and racking, stores or protects them, and refits them once the new roof and mount flashings are in place. The roofer replaces the roof in between.
Who removes the solar panels for a roof replacement?
The solar company, or a solar contractor, removes and refits the panels. We handle the roof side and coordinate the sequence with them, but we do not remove, store or refit panels.
Does removing solar panels affect the warranty?
It can. Removal and refitting may affect the solar warranty, and the new roof’s penetrations may affect the roof warranty. Ask both companies how their warranties are affected before work starts.
When is the best time to replace a roof under solar panels?
The cooler, drier months outside the monsoon season, from June 15 to September 30, are usually best. Planning ahead also gives both companies time to schedule so there are no gaps between stages.